|
DEC 2010 UPDATE
|
-
The main hall
roof was completed since July. The external of the castle was covered with a
number of coats of lime wash. Cast iron downpipes have been installed
externally. The windows arrived from the Vale Bronze Casements and were
installed during September and October. The frameless windows were installed
using specialist double glazed slimlite glass from Scotland.
-
-
On 14th
December the internal and external scaffolding was taken down by Martins
Scaffolding.
-
-
In the coming
weeks the outside will be completed with the installation of the 2 remaining
door surrounds from Edwin Feeney and the construction of the missing archway
over the main steps. The main steps will also be repaired and this area
tided up. The ground floor level lime washing will also be completed.
The adjoining coach house is almost completed and is being painted at the
current time. The externals areas will be landscaped during January and
February.
|
|
JULY 2009
UPDATE
|
- Work is progressing on the
central roof over the main hall. The timberwork has been completed and roof
has been felted.
- A number of skylights have
been installed and the slating of the roof is progressing well. This roof
will be completed by the middle of September.
-
- Externally, the bartizans have
been completed, the limestone window surrounds are being pointed and the
upper floors have been lime washed. Edwin Feeney has completed the remaining
limestone surrounds for the new front door and the existing front door at
the top of the stairs. Vale Bronze Casements windows have been manufactured
to templates provided and we expect these to be delivered in late
August.
The main focus has been on the
adjoining coach house which is now completed to roof level. We are waiting for
delivery of the windows and plastering, electrics and plumbing will start
towards the ends of August.
|
|
MARCH 2009
UPDATE
|
-
- The 4 corner tower roofs have
been now been fully completed. These were constructed in timber and steel
beams were inserted under the ridges. The roofs are composed of natural slate sourced in Spain.
In each
of the four corners, the valleys flow into specially constructed gutter
boxes, approximately 600mm x 600mm. These were formed in plywood, coated in fibre
glass and covered with lead. 3 of the four
corners are connected to an internal piping system which links the 3 outlets
and carriers the rain water back out externally through a hole cored in the wall,
where it meets the fourth corner. Using this method, we have reduced the amount of
drainage pipes externally from 16 to 8, thus improving the overall aesthetics
of the building..
-
- The limestone coping stones and
pinnacles have been covered in Code 5 lead on the four corner towers. A
similar approach will be adopted for the hall of the main roof.
-
- Bartizan reconstruction has been
completed and the upper peaks will be covered in lead in the coming weeks.
- A number window
surrounds have been installed since the last update. The remaining surrounds will be delivered by Edwin
Feeney in the coming weeks.
- Internally, the landings
around the lift-shaft were completed using the block and beam system.
-
- Focus will now move on to the
construction of the roof in the main hall. By the end of the Summer all
external works should be completed on the castle.
-
- Adjacent to the castle,
the foundations for the coach house have been completed. Masonry work has
commenced and Ducon slabs installed for the floors.
|
|
JANUARY 2009
UPDATE
|
-
Internally, much of
the castle has now been cleaned down and washed. In the south tower, the lift
shaft has been completed and the 3rd floor installed. The steel have been
inserted on the 1st and 2nd floors for the landings and these will be completed
using the t-beam and block system in early January.
-
-
Externally, all
pointing and masonry repairs have now been completed.
-
-
More limestone
window surrounds have been installed and the South East elevation is now
complete and the North East
-
elevation is almost complete. These include the 2
nine panel windows (double transomed and double mullioned).
-
-
Preliminary works
commenced on the 4 corner tower roofs with the installation of the supporting
steelworks.
-
-
All 9 chimneys have
now been covered with lead and the chimney shafts have been rendered in lime
harling and much of the scaffold for these has now been removed.
-
-
Much of the external
walls of the castle have been scratch coated with lime render and a number of
panels have been covered with lime harling.
-
-
Work has commenced
on the adjoining coach house and groundwork involving the relocation of ESB,
Eircom and the water main have been completed. The dangerous gable of the
existing structure was demolished and the stone retained on site for further
works. Foundation work has also commenced.
-
-
Over the coming
months we aim to complete the window surrounds, all external rendering and the
roofs. We will continue to focus on developing the coach house.
|
|
SEPTEMBER 2008
UPDATE
|
-
Scaffolding is being
erected internally in the Main Hall and later in the 4 corner towers.
-
-
Re-pointing is
continuing on the South West and North West Elevations.
-
-
The North East
elevation is being cleaned, de-rooted and stitched.
-
-
Remaining landing
area are being cast in the corner towers.
-
-
Work has commenced
on building the lift shaft.
-
-
A sample of Harling
was applied to the walls by "Living with the Past".
|
|
AUGUST 2008
UPDATE
|
-
The 2nd and 3rd
floors were installed in all areas with the exception of the lift (southern)
tower.
-
-
Stairs were
installed in the northern, eastern and western towers from the 2nd to the 3rd
floor.
-
-
Repointing was
completed on the South East elevation and commenced on the South West Elevation.
-
-
Cleaning, root
removal and stitching continued on the South West and North West Elevations.
-
-
Pre-cast lintels
continued to be installed internally in a number of the opes.
-
-
The cut limestone
surrounds were installed and repaired on the 3rd and 4th levels externally.
-
-
The lift shaft pit
and floor was completed in the southern tower.
-
-
Archaeological
testing was completed at the old cottage revealing a cobblestone floor in parts
of the ruin.
|
|
JULY 2008
UPDATE
|
-
The scaffolding was
completed by Martin Scaffolding.
-
-
The bulk of the
external render, foliage and roots (where appropriate) were removed from the
castle.
-
-
Steel angles were
then installed on the 2nd and 3rd floors and U-Beams in the mezzanine area of
the Main Hall.
-
-
During this activity, the remains of a window were found in the
Main hall on the North West Elevation which is evidence that the
-
external stairs
and archway was not original to the building.
-
-
Pre-cast lintels
continued to be installed internally in a number of the opes.
-
-
Work is in progress
on the South East elevation with re-pointing and preparation of the walls for
the finished harling render.
-
-
The loose coping
stones are being removed and reset where appropriate.
-
-
Some repairs to the
masonry are necessary, particularly in the corner areas where the roof valleys
meet the external stone walls. Additionally, a number of the small cracks will be
repaired in the coming weeks.
-
-
In general, the
structure of the castle is in excellent condition, with the main areas of
degradation being found where the timber lentils have failed. Additionally, on
the 2nd and 3rd floors of the Northern and Eastern towers, the masonry around
the chimney breasts requires substantial repair.
-
-
The cut limestone
surrounds were delivered by Edwin Feeney for the upper 2 levels of the structure
and work will commence on the installation of these during August.
|
|
JUNE 2008
UPDATE
|
-
The subfloors were
poured in all areas with the exception of the Southern Tower (lift shaft) and
the Western Tower (due to the cobblestone floor).
-
-
Internally, at 1st
floor level new steel angles were bolted to the walls or, where possible,
placed on bearing ledges. The existing steels at 1st floor level in the main
hall were shot-blasted and primed. The bearing ends of these were checked and
then re-set in concrete. New steel channels were inserted at the Northern and
Southern ends of the main hall and tied back to the original steel beams.
-
-
The 1st floor was
then installed throughout the castle using the block and t-beam system.
-
-
Pre-cast lintels
were installed internally in a number of the opes.
-
-
"Living
with the Past" took samples of the lime render internally and internally
and are analysing the remains of the existing render.
|
|
MAY 2008 UPDATE
|
-
Ground works
commenced on the 28th of April 2008. Externally, a land drain was laid around
the perimeter of the castle. This was necessary due to the fact that the current
road around the castle is approximately .5 meters above the original and to
prevent the ingress of dampness, the drain was laid adjacent to the external
walls. Additional drains have been laid for the patio areas and the sewer pipes
and electrical ducting have been completed.
-
-
A mains water connection was also
completed. During this work, the original drainage system was discovered around
the area of the Northern tower. This was recorded and preserved in situ.
-
-
The inner castle was
excavated to facilitate the pouring of the subfloor. The lift shaft pit was
created in Southern tower. An original cobblestone floor was uncovered in the
western tower. This has been recorded and preserved in situ. All works
were monitored by Dan Noonan Archaeological Consultancy.
-
-
There is also
evidence that a basement existed in the Northern tower.
-
-
The erection of
scaffolding also commenced in May and hardcore was laid internally in the
castle.
|